 |
|
|
|
|
EXECUTION PHASE I
WEEK 19
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
6. MAC: |
Marine Activities |
7. WTG: |
Wind Turbine Generators |
Connection
to the Elia grid succesfully tested on 05/06/2008 |
150kV
sea cable laying complete 29/09/2008 |
150kV
cable succesfully tested on 26/10/2008 |
Pull in of the
33kV cables between the wind turbines |
 |
 |
The
grid energizing of the first wind turbine took place on Thursday
11/12/2008 |
Infield
cable works completed week 16/09 |
Mobilisation
of the vessel C.S. Sovereign for the jetting of the 33kV infield
cables |
 |
 |
Burial
of the 33kV cables |
Application
of the armour layer of the scour protection around the foundations |
 |
Scour
protection armour laying at WTG D4 and D5 |
|
 |
First
C-Power kilowatt production of WTG D1 is a fact 29/12/2008 |
First
C-Power kilowatt production of WTG D2 is a fact 29/01/2009 |
First
C-Power kilowatt production of WTG D3 is a fact 24/04/2009 |
First
C-Power kilowatt production of WTG D4 is a fact 28/04/2009 |
First
C-Power kilowatt production of WTG D5 is a fact 05/05/2009 |
First
C-Power kilowatt production of WTG D4 is a fact 10/05/2009 |
All
wind turbines are operational as from Sunday May 10th 2009 |
|
|
|
Scheldedijk 30 - Haven 1025 - 2070 Zwijndrecht, Belgium - Tel. + 32-3-250 55 51 - Fax + 32-3-250 55 52 - E-mail: c-power@c-power.be |