EXECUTION PHASE I
WEEK 16
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
6. MAC: |
Marine Activities |
7. WTG: |
Wind Turbine Generators |
Connection
to the Elia grid succesfully tested on 05/06/2008 |
150kV
sea cable laying complete 29/09/2008 |
150kV
cable succesfully tested on 26/10/2008 |
Pull in of the
33kV cables between the wind turbines |
 |
 |
The
grid energizing of the first wind turbine took place on Thursday
11/12/2008 |
The
cable lay vessel STEMAT OSLO is mobilised for the execution of the
36kV infield cables between the windturbines D2 to D6 |
36kV
infield cable laying between WTG D5 and D6 |
Pull-in
of the 36kV cable in D5 and D6 |
Final
hang-off of the 36kV cable in D5 and D6 |
Infield
cable works completed week 16/09 |
Application
of the armour layer of the scour protection around the foundations |
 |
The
Thornton 1 spread barge is mobilised to complete the armour layer
of the scour protection around the GBF at the location of the infield
cables. |
Scour
protection armour laying at WTG D4 and D5 |
|
 |
First
C-Power kilowatt production of WTG D1 is a fact 29/12/2008 |
First
C-Power kilowatt production of WTG D2 is a fact 29/01/2009 |
|
|