EXECUTION PHASE I
WEEK 03
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
6. MAC: |
Marine Activities |
7. WTG: |
Wind Turbine Generators |
Connection
to the Elia grid |
150kV
sea cable laying complete 29/09/2008 |
150kV
cable succesfully tested on 26/10/2008 |
Pull in of the
33kV cables between the wind turbines |
 |
 |
The
grid energizing of the first wind turbine took place on Thursday
11/12/2008 |
Application
of the armour layer of the scour protection around the foundations |
 |
|
 |
First
C-Power kilowatt production of WTG D1 is a fact 29/12/2008 |
First
C-Power kilowatt production of WTG D2 is a fact 29/01/2009 |
All works are stopped during the winter period and will restart
end of March 2009 |
|
|