EXECUTION PHASE I
WEEK 35
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
6. MAC: |
Marine Activities |
7. WTG: |
Wind Turbine Generators |
Connection
to the Elia grid |
150kV
sea cable laying ongoing, 16km laid out of the 38km to lay |
|
 |
Filter
layer of the scour protection started at D5 |
Status
of the offshore works in week 35 see also overview progress |
Erection of wind turbine
D4 ongoing
|
4 out of the 6 wind turbines
are erected
|
Tower and nacelle of D4 loaded
out and ready for transport to the Thorntonbank
|
 |
|
|
|