1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
6. MAC: |
Marine Activities |
7. WTG: |
Wind Turbine Generators |
Connection
to the Elia grid |
150kV
sea cable laying ongoing |
|
 |
Filter
layer of the scour protection started at D5 |
Status
of the offshore works in week 34 see also overview progress |
Erection of wind turbine
D6 ongoing
|
|
|
|