EXECUTION PHASE I
WEEK 13
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
6. MAC: |
Marine Activities |
1.
OCS HVM
|
Works
on the new quay wall almost complete |
 |
Last
phase of the transport area to the quay wall |
 |
2.
HDD
|
|
3. GBF
|
|
Positioning
of the post tensioning strands D1 |
 |
Formwork for the upper platform
D2 |
Start
of the upper platform D3 |
Construction
of the fourth phase of the cylindrical part D4 |
Construction of the second
phase of the cylindrical part D6 |
Construction
of the temporary transformer building |
 |
Trenching
for onshore cables |
 |
Construction
of multi purpose pontoon Thornton 1 |
 |
Ongoing
deliveries of scour protection materials in port of Zeebrugge |
|
 |
FILTER
LAYER
|
|
 |
Dredging of foundation pits
|
|
|