EXECUTION PHASE I
WEEK 12
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
6. MAC: |
Marine Activities |
1.
OCS HVM
|
Works
on the new quay wall in progress |
 |
2.
HDD
|
|
3. GBF
|
Upper
platform under construction - control of inserts D1 |
|
 |
Positioning
of the anchor cage in the upper platform D2 |
 |
Construction
of the last phase of the cylindrical part D3 |
 |
Construction
of the fourth phase of the cylindrical part D4 |
Start
construction of the ringbeam D5 |
Construction
of the first phase of the cylindrical part D6 |
Construction
of the temporary transformer building |
 |
Trenching
for onshore cables |
 |
Construction
of multi purpose pontoon Thornton 1 |
 |
Ongoing
deliveries of scour protection materials in port of Zeebrugge |
|
 |
FILTER
LAYER
|
|
 |
Dredging of foundation pits
|
|
|