EXECUTION PHASE I
WEEK 9
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
1.
OCS HVM
|
Works
on the new quay wall in progress |
|
 |
2.
HDD
|
|
3. GBF
|
Entrance
of the electrical cables: joint between the Bellmouth and J-Tube |
 |
Mounting
of the anchor cage of the wind turbine in the upper part of the GBF D1 |
 |
 |
 |
Construction of the last phase of the cylindrical part D2 |
Construction
of the third phase of the cylindrical part D3 |
Construction
of the first phase of the cylindrical part D4 |
Reinforcement
of the last phase of the conical part D5 |
 |
Construction
of the ringbeam D6 |
|
|