EXECUTION PHASE I
WEEK 7
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
5. COF: |
Cables Ofshore |
1.
OCS HVM
|
Geogrid
and gravel layers ongoing in the transport area |
 |
2.
HDD
|
|
3. GBF
|
General
overview of the site |
|
 |
Detail
of a lifting lug |
 |
Cylindrical
part complete D1 |
Construction
of the third phase of the cylindrical part D2 |
First
phase of the cylindrical part complete D3 |
Construction
of the ringbeam D4 |
Reinforcement
of the conical part phase 3 D5 |
Last
conical part complete D6 |
Assembled
cable - 28 000m |
|
|