EXECUTION PHASE I
WEEK 3
1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
3. GBF: |
Gravity Base Foundation |
4. CON: |
Cables Onshore |
1.
OCS HVM
|
No
actions |
2.
HDD
|
|
3. GBF
|
Reinforcement
phase 1 cylindrical part D1 |
|
Last
phase conical part complete D3 |
|
Start
last phase conical part D4 |
|
Upper
part phase 1 conical part complete D5 |
|
Start
construction phase 3 conical part D6 |
|
Execution
of the directional drillings for future cable road crossings: drilling in
the Fortstraat |
 |
|
|