EXECUTION PHASE IWEEK 51
|
1. OCS HVM: | Preparation workyard Onshore Construction Site "Halve Maan" |
2. HDD: | Horizontal Directional Drilling for the landfall of the 150kV seacable |
3. GBF: | Gravity Base Foundation |
1. OCS HVM |
|
No
actions |
|
1. OCS HVM |
|
3. GBF |
|
Ringbeam
complete D1 |
![]() |
Starting
construction ringbeam D2 |
![]() |
Start
construction phase 4 conical part D3 |
![]() |
Start
construction phase 3 conical part D4 |
![]() |
Reinforcement
and formwork upper part phase 1 conical part D5 |
![]() |
Start
construction phase 2 conical part D6 |
![]() |
overview progress |