EXECUTION PHASE IWEEK 45
|
1. OCS HVM: | Preparation workyard Onshore Construction Site "Halve Maan" |
2. HDD: | Horizontal Directional Drilling for the landfall of the 150kV seacable |
3. GBF: | Gravity Base Foundation |
1. OCS HVM |
|
No
actions |
|
2. HDD |
|
3. GBF |
|
Closing
formwork phase 3 conical part D1 |
![]() |
Reinforcement
phase 2 conical part D2 |
![]() |
Formwork
upperr part phase 1 conical part D3 |
![]() |
Reinforcement
lower part phase 1 conical part D4 |
![]() |
Placing
the RockXolid soft infill of the base slab D5 |
![]() |
Reinforcement
base slab D6 |
![]() |