EXECUTION PHASE IWEEK 41
|
1. OCS HVM: | Preparation workyard Onshore Construction Site "Halve Maan" |
2. HDD: | Horizontal Directional Drilling for the landfall of the 150kV seacable |
3. GBF: | Gravity Base Foundation |
1. OCS HVM |
|
No
actions |
|
1. OCS HVM |
|
3. GBF |
|
Dismantling
of the formwork of phase1 of the conical part D1 |
![]() |
Formwork
of phase1 of the conical part D2 |
![]() |
Reinforcement
of phase1 of the conical part D3 |
![]() |
Formwork
base slab D4 |
![]() |