EXECUTION PHASE IWEEK 23
|
1. OCS HVM: | Preparation workyard Onshore Construction Site "Halve Maan" |
2. HDD: | Horizontal Directional Drilling for the landfall of the 150kV seacable |
3. GBF: | Gravity Base Foundation |
1. OCS HVM |
|
Driving
piles areas D6 and D1 Nip off piles area D6 |
Reinforcement workplatform D5 |
![]() |
![]() |
2. HDD |
|
Welding of HDPE-buizen Preparation of jack-up platform Tijl 2 at Zeebrugge |
![]() |