Cable landing onshore
The land fall of the high-voltage export cable is situated on the beach. The cable crosses the dunes by means of horizontal directional drilling (HDD - 30 m below the dune surface). At the land side of the dune crossing in Oostende, the 2 export cables are connected to 2 land cables (150 kV) which are connected to the Elia substation “Sas Slijkens”.