Menu

Effective works Phase 2 - 3

<< Back to overview

2011 : week 17

Fabrication and assemblage of the steel structures for the Jacket foundations are ongoing at different yards all over the world, (Belgium-Netherlands-United Kingdom-Poland-Germany-Spain-South Korea)

Seabed preparations by dredging at the locations of the foundations are complete for phase II of the project

The pile driving works started in area B of the windfarm on Wednesday 6th of April 2011. Steel piles of 40 to 50 m are driven into the seabed by a hammer installation mounted on the jack up platform Buzzard. These so called "pin-piles" are the anchors to seal the jacket foundations into the seabed.The length of the piles depends on the soil conditions.To assure the correct locations of the piles a template is lowered onto the seabed.

The pin-piles for the foundation of the offshore transformer station are already driven.

In area B 25% of the pin-piles are driven

Works week 17 2011 Works week 17 2011
Mounting of a midsection onto a jacket foundation.A midsection is the transition piece between the wind turbine tower and the facket foundation Loading of a pin-pile from a transport vessel onto the self elevating platform Buzzard at night