Effective works Phase 2 - 3
2011 : week 6
Continuous delivery at the onshore construction site at Ostend of the pin-piles for the Jacket foundations
Since the 19th of Januari 2011 23 piles have been delivered out of the 100 for phase II
Fabrication and assemblage of the steel structure for the Jacket foundations are ongoing at different yards all over the world, (Belgium-Poland-Germany-South Korea)