Menu

Effective works Phase 2 - 3

On November 25th, 2010 C-Power has closed the financing of the second and third phase of the 325 MW offshore wind warm on the Thornton Bank.
This financing enabled the construction of both phases that will take place between 2011 and 2013.

The second and third phases will consist of the installation of 48 WTG jacket foundations, 1 Offshore Transformer Station jacket foundation, 48 Senvion 6M wind turbines (with rated power output of 6,15 MW), the laying of infield cables and a second 150 kV export cable, as well as the installation of an offshore high voltage transformer station (OTS).

Installed OTS Phase 2 overview with neptune Installation turbine E1

2013

week 1 week 2 week 3 week 4
week 5 week 6 week 7 week 8
week 9 week 10 week 11 week 12
week 13 week 14 week 15 week 16
week 17 week 18  week 19  week 20 
 week 19 week 20 week 21  week 22 
 week 23 week 24  week 25  week 26 
week 27       
       

CPO-snow-6 566x1024 CPO-heli-2 1024x768

2012

week 1 week 2 week 3 week 4
week 5 week 6 week 7 week 8
week 9 week 10 week 11 week 12
week 13 week 14 week 15 week 16
week 17 week 18 week 19 week 20
week 21 week 22 week 23 week 24
week 25 week 26 week 27 week 28
week 29 week 30 week 31 week 32
week 33 week 34 week 35 week 36
week 37 week 38 week 39  week 40
 week 41 week 42 week 43  week 44
week 45  week 46 week 47 week 48
week 49 week 50 week 51 week 52

 

2011

  week 6 week 7 week 8
week 9 week 10 week 11 week 12
week 13 week 14 week 15 week 16
week 17 week 18 week 19 week 20
week 21 week 22 week 23 week 24
week 25 week 26 week 27 week 28
week 29 week 30 week 31 week 32
week 33 week 34 week 35 week 36
week 37 week 38 week 39 week 40
week 41 week 42 week 43 week 44
week 45 week 46 week 47 week 48
week 49 week 50 week 51