Effective works Phase 2 - 3
On November 25th, 2010 C-Power has closed the financing of the second and third phase of the 325 MW offshore wind warm on the Thornton Bank.
This financing enabled the construction of both phases that will take place between 2011 and 2013.
The second and third phases will consist of the installation of 48 WTG jacket foundations, 1 Offshore Transformer Station jacket foundation, 48 Senvion 6M wind turbines (with rated power output of 6,15 MW), the laying of infield cables and a second 150 kV export cable, as well as the installation of an offshore high voltage transformer station (OTS).