EXECUTION PHASE I

WEEK 17

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid succesfully tested on 05/06/2008

5. COF

150kV sea cable laying complete 29/09/2008
150kV cable succesfully tested on 26/10/2008
Pull in of the 33kV cables between the wind turbines
The grid energizing of the first wind turbine took place on Thursday 11/12/2008
Infield cable works completed week 16/09

6. MAC

Application of the armour layer of the scour protection around the foundations
The Thornton 1 spread barge is mobilised to complete the armour layer of the scour protection around the GBF at the location of the infield cables.
Scour protection armour laying at WTG D4 and D5

7. WTG

First C-Power kilowatt production of WTG D1 is a fact 29/12/2008
First C-Power kilowatt production of WTG D2 is a fact 29/01/2009
First C-Power kilowatt production of WTG D3 is a fact 24/04/2009

 