EXECUTION PHASE I

WEEK 14

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

150kV sea cable laying complete 29/09/2008
150kV cable succesfully tested on 26/10/2008
Pull in of the 33kV cables between the wind turbines
The grid energizing of the first wind turbine took place on Thursday 11/12/2008
The cable lay vessel STEMAT OSLO is mobilised for the execution of the 36kV infield cables between the windturbines D2 to D6
Starting of the 36kV infield cable lay between WTG D2 and D3
Pull in of the 36kV infield cable in WTG D2, second leg
Pull in of the 36kV infield cable in WTG D3, first leg

6. MAC

Application of the armour layer of the scour protection around the foundations
The Thornton 1 spread barge is mobilised to complete the armour layer of the scour protection around the GBF at the location of the infield cables.

7. WTG

First C-Power kilowatt production of WTG D1 is a fact 29/12/2008
First C-Power kilowatt production of WTG D2 is a fact 29/01/2009

 