EXECUTION PHASE I

WEEK 09

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

150kV sea cable laying complete 29/09/2008
150kV cable succesfully tested on 26/10/2008
Pull in of the 33kV cables between the wind turbines
The grid energizing of the first wind turbine took place on Thursday 11/12/2008

6. MAC

Application of the armour layer of the scour protection around the foundations

7. WTG

First C-Power kilowatt production of WTG D1 is a fact 29/12/2008
First C-Power kilowatt production of WTG D2 is a fact 29/01/2009
All works are stopped during the winter period and will restart end of March 2009

 