EXECUTION PHASE I

WEEK 50

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

150kV sea cable laying complete 29/09/2008
150kV cable succesfully tested on 26/10/2008
Pull in of the 33kV cables between the wind turbines
The grid energizing of the first wind turbine took place on Thursday 11th of December 2008

6. MAC

Application of the armour layer of the scour protection around the foundations

7. WTG

overview progress

 