EXECUTION PHASE I

WEEK 48

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

150kV sea cable laying complete 29/09/2008
150kV cable succesfully tested on 26/10/2008
Due to bad weather conditions the complete fleet is in the harbour to shelter. Per consequence no activities this week.

6. MAC

Due to bad weather conditions the complete fleet is in the harbour to shelter. Per consequence no activities this week.

7. WTG

overview progress

 