EXECUTION PHASE I

WEEK 42

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

150kV sea cable laying complete 29/09/2008
Preparation of the 150kV cable tests

6. MAC

Application of the armour layer of the scour protection around the foundations

7. WTG

 

  Scheldedijk 30 - Haven 1025 - 2070 Zwijndrecht, Belgium - Tel. + 32-3-250 55 51 - Fax + 32-3-250 55 52 - E-mail: c-power@c-power.be