EXECUTION PHASE I

WEEK 35

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

150kV sea cable laying ongoing, 16km laid out of the 38km to lay

6. MAC

Filter layer of the scour protection started at D5
Status of the offshore works in week 35 see also overview progress

7. WTG

Erection of wind turbine D4 ongoing
4 out of the 6 wind turbines are erected
Tower and nacelle of D4 loaded out and ready for transport to the Thorntonbank

 