EXECUTION PHASE I

WEEK 33

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

No activities this week due to bad weather conditions

6. MAC

No activities this week due to bad weather conditions

7. WTG

No activities this week due to bad weather conditions
overview progress

 