EXECUTION PHASE I

WEEK 31

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

150kV cable laying offshore started

6. MAC

Status of the offshore works in week 31 see also overview progress

7. WTG

Erection of the rotor and the blades of the first wind turbine D2
Erection of the second wind turbine

 