EXECUTION PHASE I

WEEK 29

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

4. CON

Connection to the Elia grid

5. COF

Pull in of the 150kV cable in the Godschalkstreet

6. MAC

Status of the offshore works in week 29 see also overview progress

7. WTG

Sail out from Ostend with the first set of towers and the first nacelle

 