EXECUTION PHASE I

WEEK 26

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

D1-D2-D3-D4-D5 en D6
Submerged on the Thorntonbank and backfilling of the foundation pits ongoing

4. CON

Connection to the Elia grid

5. COF

ETA in Ostend 150kV cable lay barge 02/07/2008

6. MAC

Status of the offshore works in week 26 see also overview progress
Infill of the gravity base foundations
Infill tower
Hydraulic infill
Dry infill
Levelling and grouting of the counter plates of the wind turbines

7. WTG

First 3 nacelles on the onshore site
Arrival of the first towers on the onshore site
Preperation of the WTG transportation jack up platforms

 