EXECUTION PHASE I

WEEK 25

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

D1-D2-D3-D4-D5 en D6
Submerged on the Thorntonbank and backfilling of the foundation pits ongoing

4. CON

Connection to the Elia grid

5. COF

150kV cable lay barge ready to leave Karlskrona

6. MAC

Status of the offshore works in week 25 see also overview progress
Infill of the gravity base foundations
Levelling and grouting of the counter plates of the wind turbines

7. WTG

Arrival of the first nacelles on the onshore site
Preparation of the WTG transportation jack up platform

 