EXECUTION PHASE I

WEEK 24

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities
7. WTG: Wind Turbine Generators

1. OCS HVM

2. HDD

3. GBF

D1-D2-D3-D4-D5 en D6
Submerged on the Thorntonbank and backfilling of the foundation pits ongoing

4. CON

Connection to the Elia grid

5. COF

Loading the 150kV cable in Karlskrona on the cable lay barge

6. MAC

Status of the offshore works in week 24 see also overview progress
Backfill of the foundation pits
Dredging of Vaargeul 1

7. WTG

Site installation started in Ostend and Zeebrugge

 