EXECUTION PHASE I

WEEK 20

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities

1. OCS HVM

2. HDD

3. GBF

Submerged on Throntonbank D1
Submerged on Thorntonbank D2
Ready for transport to Thorntonbank D3
Installation of auxillaries D4-D5-D6

4. CON

Connection to the Elia grid

5. COF

Construction of the landfall cofferdam for the pull in of the sea cable
Construction of the turntable on the cable lay barge Eide 28

6. MAC

Preparation of the gravel bed for the GBF D4
Backfill of the foundation pit of D3
Infill of D2
Dredging of Vaargeul 1
Preparation of mattresses for PEC crossing

 