EXECUTION PHASE I

WEEK 15

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities

1. OCS HVM

Works on the new quay wall complete

2. HDD

3. GBF

Painting of the splash zone D1
Upper platform complete D2
Casting concrete of the upper platform D3
Cylindrical part complete D4
Cylindrical part second phase D5
Construction of the last phase of the cylindrical part D6

4. CON

Start cable pulling of onshore cables

5. COF

nothing to report

6. MAC

Construction of multi purpose pontoon Thornton 1
Preparation of the shear leg crane Rambiz and the lifting frame for the GBF
Rambiz tug and anchorhandling vessel
Preparation of the gravel bed for the GBF

 