EXECUTION PHASE I

WEEK 13

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore
6. MAC: Marine Activities

1. OCS HVM

Works on the new quay wall almost complete
Last phase of the transport area to the quay wall

2. HDD

3. GBF

Positioning of the post tensioning strands D1
Formwork for the upper platform D2
Start of the upper platform D3
Construction of the fourth phase of the cylindrical part D4
Ringbeam complete D5
Construction of the second phase of the cylindrical part D6

4. CON

Construction of the temporary transformer building
Trenching for onshore cables

5. COF

nothing to report

6. MAC

Construction of multi purpose pontoon Thornton 1
Ongoing deliveries of scour protection materials in port of Zeebrugge
FILTER LAYER
ARMOUR LAYER
Dredging of foundation pits

 

 