EXECUTION PHASE I

WEEK 10

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore

1. OCS HVM

Works on the new quay wall in progress

2. HDD

3. GBF

Upper platform under construction D1
Start of the construction of the upper platform D2
Construction of the last phase of the cylindrical part D3
Construction of the second phase of the cylindrical part D4
Last phase of the conical part complete D5
Construction of the first phase of the cylindrical part D6

4. CON

Start of the construction of the temporary transformer building

5. COF

nothing to report

 