EXECUTION PHASE I

WEEK 8

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore

1. OCS HVM

Nothing to report

2. HDD

3. GBF

Mountin of the anchor cage of the wind turbine in the upper part of the GBF D1
Reinforcement of a part of the cylindrical part of D2
Cylindrical part complete D1
Construction of the fourth phase of the cylindrical part D2
Second phase of the cylindrical part D3
Ringbeam complete D4
Starting the last phase of the conical part D5
Starting ringbeam D6

4. CON

nothing to report

5. COF

nothing to report

 