EXECUTION PHASE I

WEEK 7

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore
5. COF: Cables Ofshore

1. OCS HVM

Geogrid and gravel layers ongoing in the transport area

2. HDD

3. GBF

General overview of the site
Detail of a lifting lug
Cylindrical part complete D1
Construction of the third phase of the cylindrical part D2
First phase of the cylindrical part complete D3
Construction of the ringbeam D4
Reinforcement of the conical part phase 3 D5
Last conical part complete D6

4. CON

nothing to report

5. COF

Assembled cable - 28 000m

 

 