EXECUTION PHASE I

WEEK 4

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation
4. CON: Cables Onshore

1. OCS HVM

No actions

2. HDD

3. GBF

Start phase 2 cylindical part D1
Formwork cylindrical part phase 1 D2
Construction ringbeam D3
Conical part last phase D4
Conical part last phase D5
Conical part phase 3 D6

4. CON

no new actions
no new overview progress

 

 