EXECUTION PHASE I

WEEK 2

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation

1. OCS HVM

No actions

1. OCS HVM

3. GBF

Start phase 1 cylindrical part D1  
Construction ringbeam D2  
Reinforcement last phase conical part D3  
Phase 3 conical part complete D4  
Concrete for upper part phase 1 conical part D5  
Construction phase 2 conical part D6  

 