EXECUTION PHASE I

WEEK 50

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation

1. OCS HVM

No actions

1. OCS HVM

3. GBF

Ringbeam ready to concrete
D1
Starting construction ringbeam
D2
Ready for concrete pourring phase 3 conical part
D3
Phase 2 conical part ready to concrete
D4
Reinforcement and formwork lower part phase 1 conical part
D5
Formwork upper part phase 1 conical part
D6
overview progress