EXECUTION PHASE I

WEEK 43

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation

1. OCS HVM

No actions

2. HDD

3. GBF

Casting concrete phase 2 conical part
D1
Formwork dismantling upper part of phase 1 conical part D2
Starting formwork lower part phase 1 conical part
D3
Dismantling formwork base slab
D4
Foundation beams
D5
Reinforcement base slab