EXECUTION PHASE I

WEEK 39

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation

1. OCS HVM

No new actions

1. OCS HVM

3. GBF

Formwork conical part D1, phase2
Formwork and reinforcement conical part D2, phase1
Reinforcement base slab D3