EXECUTION PHASE I

WEEK 22

1. OCS HVM: Preparation workyard Onshore Construction Site "Halve Maan"
2. HDD: Horizontal Directional Drilling for the landfall of the 150kV seacable
3. GBF: Gravity Base Foundation

1. OCS HVM

Driving foundation piles area D6
Excavations area D5 
Driving foundation piles transport area

2. HDD

Preparation of working area on the beach

Supply of HDPE pipes

Ferromagnetic detection & clearance cofferdam area

 

 