Effective works Phase 2 - 3

<< Back to overview

2011 : week 12

Continuous delivery at the onshore construction site at Ostend of the pin-piles for the Jacket foundations

Fabrication and assemblage of the steel structure for the Jacket foundations are ongoing at different yards all over the world, (Belgium-Netherlands-United Kingdom-Poland-Germany-South Korea)

A template that will be lowered on the seabed in order to hammer the prepiles at the correct locations arrived at the port of Antwerp, where it will be mounted on the Jack Up Platform Buzzard

The Jack Up Platform Buzzard, that will be deployed for the pre-piling operations will be mobilised from Antwerp to the Thorntonbank on Sunday the 27th of March

Seabed preparations are ongoing by dredging at the locations of the foundations