Effective works Phase 2 - 3
2011 : week 11
Continuous delivery at the onshore construction site at Ostend of the pin-piles for the Jacket foundations
Since the 19th of Januari 2011 more than 60 % of the piles for phase II have been delivered
Fabrication and assemblage of the steel structure for the Jacket foundations are ongoing at different yards all over the world, (Belgium-Netherlands-United Kingdom-Poland-Germany-South Korea)
The fabrication of a pre-piling template, that will be lowered on the prepared seabed in order to hammer the piles at the correct location, is ongoing
The template is almost ready for shipment to the port of Antwerp where it will be mounted on the Jack Up Platform Buzzard
Seabed preparations ongoing by dredging at the locations of the foundations
Pre-lay grapnel run is ongoing at the locations of the future infield cables and on the trajectory of the second export cable before cable laying
a jacket foundation assembly