2011 : week 10

Continuous delivery at the onshore construction site at Ostend of the pin-piles for the Jacket foundations

Since the 19th of Januari 2011 54 piles have been delivered out of the 100 for phase II

Fabrication and assemblage of the steel structure for the Jacket foundations are ongoing at different yards all over the world, (Belgium-Netherlands-Poland-Germany-South Korea)

The fabrication of a pre-piling template, that will be lowered on the prepared seabed in order to hammer the piles at the correct location, is ongoing

Vessels mobilised and seabed preparations started by dredging at the locations of the foundations

Works week 10 2011 Works week 10 2011
a jacket foundation assembly a midsection ready to be mounted on a jacket foundation